This page last changed on Sep 25, 2008 by hiroki.
Attendees: Scott and Hiroki
Duration: 11am PT->12:30 PT. (90 minutes)
Status
- we can preview activities now
Things to get done:
- clean up things we did last time so it's not specific to DIY project service. i.e. ExternalProjectService
- setup run, create workgroup. <- needs "saving project to database" to work first.
- update sail-portal at Concord (20 minutes)
- decide how to split up work, if needed
- see how it goes today and next week
- not strict timelines at this moment.
Things we got done:
- clean up things we did last time so it's not specific to DIY project service. i.e. ExternalProjectService
- started working on importing project to local db.
- made ExternalProjectService interface that extends ProjectService interface, and made DIYProjectService implement that.
- decided to save ProjectService into local db.
- updated sail-portal at Concord (20 minutes). It now has the preview functionality
|